Welcome to THE FORESTIAS, the ‘Enchanted Community District in the Forest’, where nature, animals, and humans will live together in a world-first sustainable district for happy, healthy living.
THE FORESTIAS offers every amenity for an upscale lifestyle in a forested neighborhood across 398 rai at Bangna-Trad Road Km 7 with a project value of THB125 billion. Designed with an ‘intergeneration’ concept to build family bonds and connect all generations, the development features 4 distinct residential concepts: Mulberry Grove (Villas & Condominiums), Whizdom Condominiums, The Aspen Tree Residences, and Six Senses Residences.
THE FORESTIAS will be also home to a 6-star boutique hotel, a community and family center, and a host of leisure and lifestyle amenities, including shops, restaurants, markets, offices, community spaces, and 30 rai of forest to explore together.
The forestias
Monthly progress : Mar 2024
Happitat: The New Themed Destination of Happiness
Happitat turns everyday places into vibrant spaces to create happiness for all, for multi-generational communities and visitors from afar. Here they are dazzled by the most magical and awe-inspiring experiences that shape a lifetime of memories.
A DESTINATION DESIGNED AROUND ALL GENERATIONS
Across 3 buildings with nature-inspired pathways, Happitat offers lifestyle and family entertainment facilities, food & beverage outlets, activities for art & cultural pursuits, theater, community markets, and commercial spaces for offices.
FESTIE TOWN
The celebration epicenter of Happitat brings events and festivals to life. Festie Town thrills visitors and delights residents with dazzling designs and fine dining experiences.
“Festie Town” construction (91.22%)
Structure 100%
Architecture 96.51%
Systems 96.57%
Building frame & glass 75.02%
Interiors 59.91%
Landscape 90%
Mulberry grove - villas
Monthly progress : Mar 2024
Mulberry Grove The Forestias Villas construction progress in March 2024
Phase 1.2
Overall 94.50%
Piling 100%
Structure work 100%
Architecture work 99%
MEP 95%
Façade work 94%
Interior 92%
External 90%
Interior decoration is underway including the installation of windows. Landscape architecture has begun. Systems are in testing to prepare for completing the model homes.
Phase 2
Overall 22.06%
Piling 100%
Structure work 81%
Architect work 10%
MEP 20%
Façade work 20%
Structural work is nearing completion. Architectural work has begun and preparations are underway to install building elements including façades.
Six Senses Residences The Forestias
Monthly progress : Apr 2024
Phase 1: Model House
Completion of the model house continues with system installation, building assembly, and interior and exterior decorations. Work is also underway on common areas, gardens, landscaping, and the club. Construction work on the roof has begun. Shutters and glass are being installed. Equipment is being installed in the playground and outdoor gym.
Overall Construction = 98.20%
Piling Work = 100%
Structure = 100%
Architecture = 98%
MEP Work = 96%
External Work = 97%
Phase 2: 23 Houses
Piling and roads within the project are 100% complete. Construction of the house structures is now starting.
Overall construction for the entire project is 31.81% complete.
The Forestias Signature Series
Monthly progress : Mar 2024
Construction progress for The Forestias Signature Series in March 2024
Structural work continues with the completion of concrete pouring on level 7 (mockup floor). Architectural work is progressing with the installation of TEXCA wall on level 5. MEP work continues in parallel with architectural work.
Other work includes the wastewater treatment pond (95% complete), retention tank (100%), and the installation of 2 tower cranes and 2 sets of passenger lifts for construction support.
Overall construction 20.95%
Piling works 100.00%
Structural + architectural work 13.31%
MEP work 1.15%
Exterior work 0.00%