Construction Progress

THE ASPEN TREE AT THE FORESTIAS

May-2022
May-2022
May-2022
May-2022

CONSTRUCTION UPDATE FOR May-2022

18%

All piling work is complete (Zone A - 100%, Zone B - 100%) Soil Protection work (Pit A1 - 100%, Pit A2 - 100%, Pit B - 100%) Underground work ( IL Condo -100% , Sky Villa - 100% ,High Care - 100% ,Club House - 100%,Outside building -56.46%) Superstructure ( IL Condo -19.75% , Sky Villa - 67.10% ,High care - 38.88% , club House - 7.24% ,Ground floor - 24.69% )

Structural Work

36%

System Installation

0%

Architectural Work

0%

PROJECT DEVELOPMENT TEAM

Developer:

Royal Aspen MQDC Town Limited

Architect of record:

The Beaumont Partnership

Design Consultant:

Perkins Eastmans (USA)

Senior Living Consultant and Community Operator:

Baycrest Global Solutions (Canada)

Interior Designer:

Studio 54

Landscape Designer:

PLandscape

Health and Brain Center Interior Designer:

DWP

Structure Engineer:

Infra

MEP Engineer:

EEC

Traffic Engineer:

Meinhardt (Thailand)

Lighting Designer:

Be-Lit

Sustainable Design Consultant:

Atelier Ten

Construction Management Consultant:

Stonehenge Inter

Main Contractor:

Ritta

MQDC