PROJECT NAME : The Aspen Tree The Forestias

Monthly progress : Jan 2022

Overall Construction Progress 13.14%
All piling work and soil protection work is 100% completed. Underground work in progress for Active Living Condominiums - - 98%, Sky Villa Residences - 100%, Health & Brain Center - 85.55% , Wellness Club House - 60.15%. Superstructure for Active Living Condominiums - 1.31%, Sky Villa - 14.68%, Ground Floor 24.69%
Structural Work 27.64%
System Installation 0%
Architectural Work 0%