39% Complete

Whizdom Essence Sukhumvit

Construction Update for September, 2017.


By the end of September 2017 more than 39% of work had been completed. The building structure is now finished up to the 30th floor. Unit architecture and sanitation systems for levels 22-25 are also complete.

In October 2017, structural work is set to finish up to the 32nd story. Architectural and sanitation system work is also due to begin on levels 26-30. Visavapat Co. Ltd. continues to oversee all structural and architectural construction work. Tri-En Solution Co. Ltd. remains in charge of electrical, communications, sanitation, and firefighting systems, including other subsystems.