PROJECT NAME : Mulberry Grove The Forestias villas

Monthly progress : Dec 2024

Mulberry Grove The Forestias Villas construction progress in December 2024

The project has completed structural work, started architectural masonry and plastering, and is preparing for building system installations and façade work.

Overall                          5ุ6.0%
Piling                            100%
Structure work            93.00%
Architecture work       35.40%
MEP                            35.00%
Façade work                44.20%