Mulberry Grove The Forestias Villas construction progress in March 2025
The project has completed structural work, started architectural masonry and plastering, and is preparing for building system installations and façade work.
Overall 58.5%
Piling 100%
Structure work 95.40%
Architecture work 37.50%
MEP 37.50%
Façade work 47.00%