Mulberry Grove The Forestias Villas construction progress in April 2025
The project has completed structural work, started architectural masonry and plastering, and is preparing for building system installations and façade work.
Overall 59.0%
Piling 100%
Structure work 95.50%
Architecture work 38.50%
MEP 37.75%
Façade work 47.75%