Mulberry Grove The Forestias Villas construction progress in March 2026

The project has completed structural work, started architectural masonry and plastering, and is preparing for building system installations and façade work.

Overall                          60.50%
Piling                            100.00%
Structure work            95.60%
Architecture work       40.80%
MEP                            40.00%
Façade work                53.50%