PROJECT NAME : Mulberry Grove The Forestias villas

Monthly progress : Aug 2026

Mulberry Grove The Forestias Villas construction progress in August 2026

The project has completed structural work, started architectural masonry and plastering, and is preparing for building system installations and façade work.

Overall                          60.90%
Piling                            100.00%
Structure work            95.65%
Architecture work       42.50%
MEP                            41.50%
Façade work                54.50%