Mulberry Grove The Forestias Villas construction progress in October 2026
The project has completed structural work, started architectural masonry and plastering, and is preparing for building system installations and façade work.
Overall 60.93%
Piling 100.00%
Structure work 95.75%
Architecture work 43.50%
MEP 42.00%
Façade work 54.75%