PROJECT NAME : Mulberry Grove The Forestias Condominiums

Monthly progress : Dec 2022

The car park ramp is now 100% complete. Towers T1-T6 are under construction. Architectural structure and installation are in progress for each floor.

Overall construction progress = 17.17%

  • Piling work =100%
  • Structure = 60.79%
  • Architecture work = 1.00%
  • MEP work = 3.24%
  • External work = 1.60%