Building structure is now complete from the ground floor to the roof. The 2-storey underground parking structure is also 100% finished. Sliding glass doors and fixed doors are now being installed. The installation of building systems and interior decoration is also underway. Exterior architectural work is now at the stage of placing soil and plant containers to complete the project’s landscape.
Overall Construction = 25.86%
Piling Work = 100%
Architecture = 10%
MEP Work = 19.71%
External Work = 20.70%