PROJECT NAME : Mulberry Grove The Forestias Condominiums

Monthly progress : May 2023

Underground carpark floors for all 6 buildings are 100% complete. Construction from the 1st floor to the roof is 100% finished for T1, T2, and T3 buildings and 90-95% complete for buildings T4, T5, and T6. In architectural work, sliding glass and fixed panels have been installed along with building systems and interior decoration. In exterior work, the landscape has been filled and various containers installed for decoration.

 

Overall Construction = 41.06%
Piling Work = 100%
Architecture = 29.95%
MEP Work = 38.39%
External Work = 25%