The project is in phase 1. The first 3 show houses and the Clubhouse are now undergoing interior decoration, landscape, and exterior work. The other 5 model houses are in architectural construction.
Construction Progress Phase 1 62.30%
Piling Work 100%
Structural Work 92%
System Installation 60%
Architectural Work 70%
External Work 70%