Construction of 3 show homes as well as the clubhouse and the common area for Phase 1.1 is now complete. Architectural work, system work, interior work, and exterior aluminum glass work is underway for the villa in Phase 1.2.
Phase 2 piling is underway and work has begun on the car park structure, including preparation work for the main contractor.
Phase 1.1 Overall Construction Progress 100%
Phase 1.2 Overall Construction Progress 76%
Phase 2 Overall Construction Progress 3%