PROJECT NAME : Mulberry Grove The Forestias villas

Monthly progress : Jul 2023

Mulberry Grove The Forestias Villas Construction Update: July 2023

 Overall construction for phase 1

Construction of the glass and aluminum building facade is underway, as well as interior and exterior work.

 Overall progress phase 1.1               100%

 Overall progress phase1.2                85%

  • Piling                      100%
  • Structure work        100%
  • Architecture work    90%
  • Façade work           87%
  • MEP                        85%
  • Interior                     67%
  • External                  68%

Overall construction for phase 2

Piling work is now near completion with work underway for external roads. In building structure work, concrete is being poured for the basement carpark. Preparation is underway for pouring concrete for 1st and 2nd floor structures.

Overall progress phase 2       5.6%

  • Piling                      98%
  • Structure work        23%