PROJECT PROGRESS
chevron-left chevron-right facebook facebook twitter link chat

PROJECT NAME : Mulberry Grove The Forestias villas

Monthly progress : Dec 2023

Construction progress for Mulberry Grove The Forestias Villas in December 2023

Phase 1.2
Overall construction              93%
Piling work                           100%
Structure work                     100%
Architecture work                99%
Façade work                        93%
MEP                                   93%
Interior                               85%
External                              80%

Construction and interior decoration of 5 model homes is underway, including the aluminum and glass building envelope and the installation of furniture and decorations.

 

Phase 2
Overall construction              12%
Piling work                          100%
Structure work                    70%
Architecture work                 2%

Construction of 29 houses is underway. Structural and architectural work is starting, including preparation for installing the building assembly systems.