Mulberry Grove The Forestias Villas construction progress in March 2024
Phase 1.2
Overall 94.50%
Piling 100%
Structure work 100%
Architecture work 99%
MEP 95%
Façade work 94%
Interior 92%
External 90%
Interior decoration is underway including the installation of windows. Landscape architecture has begun. Systems are in testing to prepare for completing the model homes.
Phase 2
Overall 22.06%
Piling 100%
Structure work 81%
Architect work 10%
MEP 20%
Façade work 20%
Structural work is nearing completion. Architectural work has begun and preparations are underway to install building elements including façades.