Mulberry Grove The Forestias Villas construction progress in June 2024
Phase 1.2
Currently in the process of interior decoration work. Begin landscape architecture work on the outside of the building. and test the system to prepare for fixing defects for delivery of sample homes.
Overall 96%
Piling 100%
Structure work 100%
Architecture work 99%
MEP 96%
Façade work 96%
Interior 94%
External 93%
Phase 2
Overall, the project is in the process of being completed with structural work. Begin architectural work - plastering Begin preparing for installation of building assembly systems. Begin building façade work.
Overall 24.60%
Piling 100%
Structure work 86%
Architect work 14%
MEP 20%
Façade work 26%