Mulberry Grove The Forestias Villas construction progress in June 2024
Phase 1.2
Currently in the process of interior decoration work. Begin landscape architecture work on the outside of the building. and test the system to prepare for fixing defects for delivery of sample homes.
Overall 97%
Piling 100%
Structure work 100%
Architecture work 99%
MEP 97%
Façade work 97%
Interior 95%
External 94%
Phase 2
Overall, the project is in the process of being completed with structural work. Begin architectural work - plastering Begin preparing for installation of building assembly systems. Begin building façade work.
Overall 25.30%
Piling 100%
Structure work 86%
Architect work 16%
MEP 20%
Façade work 26%