Mulberry Grove The Forestias Villas construction progress in October 2024
Phase 1.2: Interior decoration is underway, landscaping is starting, and system tests are underway to resolve defects before delivering the model home.
Phase 2: The project has completed structural work, started architectural masonry and plastering, and is preparing for building system installations and façade work.
Overall 55.5%
Piling 100%
Structure work 90.92%
Architecture work 30.40%
MEP 31.84%
Façade work 43.19%