PROJECT PROGRESS
chevron-left chevron-right facebook facebook twitter link chat

PROJECT NAME : Mulberry Grove The Forestias villas

Monthly progress : Oct 2024

Mulberry Grove The Forestias Villas construction progress in October 2024

 

Phase 1.2: Interior decoration is underway, landscaping is starting, and system tests are underway to resolve defects before delivering the model home.

Phase 2: The project has completed structural work, started architectural masonry and plastering, and is preparing for building system installations and façade work.

Overall                          55.5%
Piling                            100%
Structure work            90.92%
Architecture work       30.40%
MEP                            31.84%
Façade work                43.19%