PROJECT NAME : The Forestias Signature Series

Monthly progress : Sep 2023

In structural and MEP work, preparation is underway for pouring concrete on the ground floor. Floor slabs are 70% installed and concrete reinforcement rebars, beams, and slabs are 30% complete. The wastewater treatment pond is 80% finished with the retention tank and installation of 2 tower cranes now 100% complete. Overall construction​​​ 8.47% Piling works​​​ 100.00% Structural and architectural work​ 8.97% MEP work​​​ 0.29% Exterior work ​​​​ 0.00%