Construction progress for The Forestias Signature Series in March 2024
Structural work continues with the completion of concrete pouring on level 7 (mockup floor). Architectural work is progressing with the installation of TEXCA wall on level 5. MEP work continues in parallel with architectural work.
Other work includes the wastewater treatment pond (95% complete), retention tank (100%), and the installation of 2 tower cranes and 2 sets of passenger lifts for construction support.
Overall construction 20.95%
Piling works 100.00%
Structural + architectural work 13.31%
MEP work 1.15%
Exterior work 0.00%