Roofing and installation of building materials in the villas are underway. Interior architecture and decoration work has begun. The clubhouse’s roof and building systems are in progress. Road structure is being poured and landscape enhancement for exterior work is underway. The model house phase 1 is set to be completed in the second quarter of 2023.
Overall construction for phase 1 61.19 %
Piling work 100 %
Architecture 59.77 %
MEP work 49.13 %
External work 41.31%