Phase 1
Construction of villa roof systems and architectural work is underway as well as installation of doors and windows. The clubhouse’s roof is in the process of installation. Landscape architecture work is starting, along with road work and construction of a security guardhouse.
Overall construction 70.29%
Piling 100%
Architecture 58.05%
MEP 74.07%
Exterior work 68.43%