PROJECT PROGRESS
chevron-left chevron-right facebook facebook twitter link chat

PROJECT NAME : Six Senses Residences The Forestias

Monthly progress : Aug 2023

Phase 1
Show House Construction Phase 1
The house structure is now complete and architectural elements are being installed, including the building system, doors, windows, and interior work. Various decorative aspects are underway. The clubhouse roof is in place. Ground-floor decoration has begun as well as exterior work. Landscape architecture, landscaping, road works, guardhouses are also in the process of gathering and installing decorative materials.

Overall construction                            82.26%
Piling                                                   100%
Architecture                                        74.15%
MEP                                                     92.68%
Exterior work                                       95.16%