PROJECT PROGRESS
chevron-left chevron-right facebook facebook twitter link chat

PROJECT NAME : Six Senses Residences The Forestias

Monthly progress : Apr 2024

Phase 1: Model House
Completion of the model house continues with system installation, building assembly, and interior and exterior decorations. Work is also underway on common areas, gardens, landscaping, and the club. Construction work on the roof has begun. Shutters and glass are being installed. Equipment is being installed in the playground and outdoor gym.
Overall Construction = 98.20%
Piling Work ​​= 100%
Structure ​​= 100%
Architecture ​​= 98%
MEP Work ​​= 96%
External Work ​​= 97%

Phase 2: 23 Houses
Piling and roads within the project are 100% complete. Construction of the house structures is now starting.
Overall construction for the entire project is 31.81% complete.