PROJECT PROGRESS
chevron-left chevron-right facebook facebook twitter link chat

PROJECT NAME : The Aspen Tree The Forestias

Monthly progress : Nov 2021

Overall Construction Progress 9.66%
All piling work and soil protection work is 100% completed. Underground work in progress for Active Living Condominiums - 97.37%, Sky Villa Residences - 95.28%, Health & Brain Center - 74.94% , Wellness Club House - 44.35%.  Superstructure for Active Living Condominiums - 0.83%, and Sky Villa - 1.56%
Structural Work 24.25%
System Installation 0%
Architectural Work 0%