Overall Construction Progress 17.50%
All piling work is complete (Zone A - 100%, Zone B - 100%)
Soil Protection work (Pit A1 - 100%, Pit A2 - 100%, Pit B - 100%)
Underground work ( IL Condo -100% , Sky Villa - 100% ,High Care - 100% ,Club House - 100%,Outside building -56.46%)
Superstructure ( IL Condo -19.75% , Sky Villa - 67.10% ,High care - 38.88% , club House - 7.24% ,Ground floor - 24.69% )
Structural Work 35.50%
System Installation 0%
Architectural Work 0.11%