OVERALL CONSTRUCTION PROGRESS 19.20%Soil Protection system & Excavation work are finish. This Month we continuous the structure work & architect work.STRUCTURE WORK 40.0%SYSTEM INSTALLATION 0.8%ARCHITECTURAL WORK 1.05%