OVERALL CONSTRUCTION PROGRESS 20.90%Soil Protection system & Excavation work are finished. We continued the structural work and architectural work this month.STRUCTURE WORK 65.0%SYSTEM INSTALLATION 0.90%ARCHITECTURAL WORK 6.66%