PROJECT PROGRESS
chevron-left chevron-right facebook facebook twitter link chat

PROJECT NAME : The Aspen Tree The Forestias

Monthly progress : Dec 2022

OVERALL CONSTRUCTION PROGRESS  38.40%
STRUCTURE WORK 96.39%
SYSTEM INSTALLATION 13.57%
ARCHITECTURAL WORK 24.76%