PROJECT PROGRESS
chevron-left chevron-right facebook facebook twitter link chat

PROJECT NAME : The Aspen Tree The Forestias

Monthly progress : Jun 2023

Overall Construction Progress 61.01%
Structural Work 100%
System Installation 47.66%
Architectural Work 75.64%