PROJECT PROGRESS
chevron-left chevron-right facebook facebook twitter link chat

PROJECT NAME : The Aspen Tree The Forestias

Monthly progress : Oct 2023

Overall Construction Progress 77.46%
Structural Work 100%
System Installation 72.72%
Architectural Work 91.06%