PROJECT NAME : The Forestias

Monthly progress : May 2022

The Forestias Project Progress: May 2022

Our “Community Center”, “Family Center”, and “Town Center” are spaces where residents can relax and connect. Each of these amenities reflects the values of “The Forestias” to enhance the lifestyles and well-being of residents and visitors.

Key attractions include a vintage cinema and top tutorial colleges. Restaurants will serve organic food that’s both nutritious and delicious, with tasty desserts, drinks, and pastries as well as vegetarian options. We’ll also have plant and flower shops, clinics, fitness studios, and a choice of markets.

  • The Community Center’s overall progress is now 18.89%, with foundation work 18.13% and excavation work 100% complete.
  • The Family Center’s overall progress is 10.89%, with foundation work 5.88% and excavation work 100% complete.
  • The Town Center’s overall progress is 14.02%, with foundation work 32.77% and excavation work 100% complete.