PROJECT PROGRESS
chevron-left chevron-right facebook facebook twitter link chat

PROJECT NAME : The Forestias

Monthly progress : Dec 2022

The Central Utilities Plant (CUP) is a new “smart city” infrastructure system to help achieve environmental sustainability.

The CUP enables a “district energy” approach, supplying chilled water through a network of tunnels to cool all the residences and buildings across the site.

Overall progress is 87.05%
- Building structure is 100% complete and architecture is 93% finished, with completion set for December 2022.
- The thermal energy storage tank is 83% complete.
- Mechanical systems are 81% complete.
- Electrical work is 85% complete.
- 60% of the district cooling system is now in testing and commissioning.