PROJECT NAME : The Forestias

Monthly progress : Apr 2023

The “Community Center”, “Family Center”, and “Town Center” are spaces to relax and connect. Each amenity reflects the values of “The Forestias” to enhance the lifestyles and well-being of residents and visitors.

Key attractions include a vintage cinema and top tutorial colleges. Restaurants will serve organic food that’s both nutritious and delicious, with tasty desserts, drinks, and pastries as well as vegetarian options. We’ll also have plant and flower shops, clinics, fitness studios, and a choice of markets.

“Community Center” construction (53.91%)
Structural work
Basement 100% complete
Floors 1-6 100% complete
Floor 7 in progress and due to complete on 30/05/2023

Architectural work
Floors B2-B3 90% complete
Floor B1 55% complete
Floor 1 45% complete
Floor 2 15% complete

Mechanical, electrical, plumbing (MEP)
Floors B2-B3 65% complete
B1 floor 40% complete
Floor 1 10% complete

“Family Center” construction (40.23%)
Structural work
Basement 100% complete
Floors 1-4 100% complete
Floor 5 78% complete and due to complete on 25/05/2023

Architectural work
Floors B2-B3 90% complete
B1 floor 60% complete
Floor 1 20% complete

Mechanical, electrical, plumbing (MEP)
Floors B2-B3 65% complete
B1 floor 40% complete
Floor 1 5% complete