PROJECT NAME : The Forestias

Monthly progress : Jun 2023

The central utility plant (CUP) provides new “smart city” infrastructure to help achieve environmental sustainability.

The CUP enables a “district energy” approach, supplying chilled water through a network of tunnels to cool all the residences and buildings across the site.

  • Central utility plant construction is 100% complete.
  • Building structure and architecture are both 100% complete.
  • Thermal energy storage tank is 100% complete.
  • Mechanical, electrical, plumbing (MEP) work is 100% complete.
  • District cooling system and its testing and commissioning are 100% complete.
  • Test run of district cooling system, chiller, and connection to cold-water pipe system and project tunnels are 100% complete.