Progress

December 2017
 
100% Complete

Whizdom Connect Sukhumvit Construction Update, December 2017


By the end of December 2017 work is 100% complete. The project's shared facilities and garden are 100% finished. Sanitation and electrical systems are 100% complete. Visavapat Co. Ltd. continues to oversee all structural and architectural construction. Tri-En Solution Co. Ltd. remains in charge of electrical, communications, sanitation, and firefighting systems, including other subsystems.