Mulberry Grove The Forestias Villas construction progress in March 2024
Phase 1.2
Installation of aluminum and glass interior fixtures is underway. Exterior landscaping is ready to start along with system tests to prepare for delivery of the model house.
Overall 95%
Piling 100%
Structure work 100%
Architecture work 99%
MEP 95%
Façade work 95%
Interior 93%
External 93%
Phase 2
Structural construction is nearing completion. Preparations have begun for the installation of building systems and building façade work.
Overall 22.06%
Piling 100%
Structure work 81%
Architect work 10%
MEP 20%
Façade work 20%