Piling is now completed. Construction of foundations and basement walls (B1, B2) is underway with checks under the MQDC Standard for construction quality (BIM). Other work is in preparation.
Overall Construction Progress 10.23%
Piling Work 100%
Structural Work 33%
System Installation 1%
Architectural Work 1%
External Work 1%