PROJECT NAME : Mulberry Grove The Forestias villas

Monthly progress : Nov 2024

Mulberry Grove The Forestias Villas construction progress in November 2024

The project has completed structural work, started architectural masonry and plastering, and is preparing for building system installations and façade work.

Overall                          55.7%
Piling                            100%
Structure work            91.00%
Architecture work       31.40%
MEP                            32.00%
Façade work                43.20%