Mulberry Grove The Forestias Villas construction progress in January 2025
The project has completed structural work, started architectural masonry and plastering, and is preparing for building system installations and façade work.
Overall 56.5%
Piling 100%
Structure work 95.00%
Architecture work 36.40%
MEP 36.00%
Façade work 45.00%