PROJECT PROGRESS
chevron-left chevron-right facebook facebook twitter link chat

PROJECT NAME : The Aspen Tree The Forestias

Monthly progress : Aug 2021

Overall Construction Progress 7.15%
Underground work in progress for Active Living Condominiums - 75.13%, Sky Villa Residences - 85.67%, Health & Brain Center - 47.72% , Wellness Club House - 43%. All piling work and soil protection work is 100% completed.
Structural Work 21.53%
System Installation 0%
Architectural Work 0%