PROJECT PROGRESS
chevron-left chevron-right facebook facebook twitter link chat

PROJECT NAME : The Forestias

Monthly progress : Nov 2023

The “Community Center”, “Family Center”, and “Town Center” are spaces to relax and connect. Each amenity reflects the values of “The Forestias” to enhance the lifestyles and well-being of residents and visitors.

Key attractions include a vintage cinema and top tutorial colleges. Restaurants will serve organic food that’s both nutritious and delicious, with tasty desserts, drinks, and pastries as well as vegetarian options. We’ll also have plant and flower shops, clinics, fitness studios, and a choice of markets.

“Community Center”- construction (76.40%)
Structural work: 
100% complete
Architectural work (48.78%)
Floors B1-B3: 95.0% complete
Floor 1: 40.5% complete
Floor 2: 29.0% complete
Floor 3: 29.5% complete
Floor 4: 25.5% complete
Floor 5: 39.5% complete
Floor 6: 40.0% complete
Floor 7: 11.25% complete

Mechanical, electrical, plumbing (MEP) (31.43%)
Floors B1-B3: 95% complete
Floor 1: 40% complete
Floor 2: 30% complete
Floor 3: 25% complete
Floor 4: 20% complete
Floor 5: 5% complete
Floor 6: 5% complete

“Family Center” construction (74.15%)
Structural work:
100% complete
Architectural work
(52.85%)
Floors B1-B3: 100% complete
Floor 1: 60% complete
Floor 2-5: 40% complete
Floor 6-10: 50% complete
Floor 11-16: 20% complete

Mechanical, electrical, plumbing (MEP) (38.55%)
Floors B1-B3: 95% complete
Floor 1: 45% complete
Floor 2: 45% complete
Floor 3 : 35% complete
Floor 4-16: 5% complete