Construction progress for Mulberry Grove The Forestias Villas in December 2023
Phase 1.2
Overall construction              93%
Piling work                           100%
Structure work                     100%
Architecture work                99%
Façade work                        93%
MEP                                   93%
Interior                               85%
External                              80%
Construction and interior decoration of 5 model homes is underway, including the aluminum and glass building envelope and the installation of furniture and decorations.
Phase 2
Overall construction              12%
Piling work                          100%
Structure work                    70%
Architecture work                 2%
Construction of 29 houses is underway. Structural and architectural work is starting, including preparation for installing the building assembly systems.