Mulberry Grove The Forestias Villas construction progress in September 2024
Phase 1.2: Interior decoration is underway, landscaping is starting, and system tests are underway to resolve defects before delivering the model home.
Phase 2: The project has completed structural work, started architectural masonry and plastering, and is preparing for building system installations and façade work.
Overall                          55%
Piling                            100%
Structure work            90.02%
Architecture work       29.42%
MEP                            31.42%
Façade work                43.19%