Mulberry Grove The Forestias Villas construction progress in October 2024
The project has completed structural work, started architectural masonry and plastering, and is preparing for building system installations and façade work.
Overall                          55.5%
Piling                            100%
Structure work            90.92%
Architecture work       30.40%
MEP                            31.84%
Façade work                43.19%