Mulberry Grove The Forestias Villas construction progress in October 2025
The project has completed structural work, started architectural masonry and plastering, and is preparing for building system installations and façade work.
Overall 60.10%
Piling 100.00%
Structure work 95.52%
Architecture work 39.85%
MEP 39.00%
Façade work 50.20%