CONSTRUCTION UPDATE FOR December-2022

38%

Soil Protection system & Excavation work are finish. We continued the structural work and architectural work this month.

Structural Work

96%

System Installation

14%

Architectural Work

25%

PROJECT DEVELOPMENT TEAM

Developer:

Royal Aspen MQDC Town Limited

Architect of record:

The Beaumont Partnership

Design Consultant:

Perkins Eastmans (USA)

Senior Living Consultant and Community Operator:

Baycrest Global Solutions (Canada)

Interior Designer:

Studio 54

Landscape Designer:

PLandscape

Health and Brain Center Interior Designer:

DWP

Structure Engineer:

Infra

MEP Engineer:

EEC

Traffic Engineer:

Meinhardt (Thailand)

Lighting Designer:

Be-Lit

Sustainable Design Consultant:

Atelier Ten

Construction Management Consultant:

Stonehenge Inter

Main Contractor:

Ritta

MQDC
Confirmation